Roadway

Paul Brown Stadium Road Improvements

Turner-Barton Malow

Contract Value: $4,300,000
Completed in 2001
This project consisted of replacing Mehring Way and Central Avenue, which surround Paul Brown Football Stadium in Cincinnati, OH Work included concrete pavement, sewers, landscaping, and pavers.

Wayne & Wilmington Intersection Improvements

City of Dayton

Completed in 2011
Contract Value: $2,600,000
This project included roadway widening and reconstruction at the Insection of Wayne Ave and Wilmington Ave. in Dayton, OH.

Center Hill Ave. Bridge

City of Cincinnati Department of Transportation & Engineering

Completed in 2013
Contract Value: $3,400,000
Replaced a 150 foot long two lane three span reinforced concrete bridge over Mill Creek with a 150 foot long two lane two span prestressed concrete I-beam bridge on driven pipe piles.

SR32 & Eastgate Blvd. Reconfiguration

Ohio Department of Transportation

Completed in 2014
Contract Value: $9,039,000
Reconfiguration of the SR 32 Eastgate Blvd interchange. Construction of bridge ramp.

Blue Ash - Carver Road Rehab

City of Blue Ash

Completed in 2014
Contract Values: $1,800,000
This project included the replacement of Carver Rd., a sidewalk addition along Reed Hartman Hwy, and the construction and installation of 2 new pedestrian bridges.

Austin Blvd. Reconstruction

Montgomery County

Completed in 2014
Contract Values: $3,450,000
This project consisted of widening Austin Blvd. on both sides, the widening of a box beam bridge and installation of a 2x4 box culvert. Other work included: water main lowering and rerouting roadway around the bridge.

MLK Blvd. & High St. Intersection Improvement

City of Hamilton

Completed in 2017
Contract Values: $2,550,000
This Intersection improvement project included the addition of dual left turn lanes Southbound and a right turn lane Westbound. Project also included the construction of a new Retaining Wall.

OSU Athletics District Road and Storm Water

Ohio State University Columbus, OH

Completed in 2017
Contract Values: $5,380,000
This project included site utilities, storm, water, demolition, abatement, parking lot construction, roadway and box culverts,a wetlands/retention pond along with hardscape and landscaping for OSU Athletics next to Woody Hayes Facility to accommodate new sports complex.

Route 4 Bypass

City of Fairfield, OH

Completed in 2013
Value: $9,250,000
This project included the widening of SR 4 Bypass from 2 lanes to 4 lanes with additional turn lanes at intersections. The intersection was modified to divert left turn movements via a constructed diversion road. Additional work in the project over CRX Transportation Inc. Railroad crossing included the rehab of the existing bridge structure and the addition of a new bridge adjacent.
Paul Brown Stadium Roadway Construction Project

Paul Brown Stadium Road Improvements

Turner-Barton Malow

Value: $4,300,000

Completed in 2001
This project consisted of replacing Mehring Way and Central Avenue, which surround Paul Brown Football Stadium in Cincinnati, OH Work included concrete pavement, sewers, landscaping, and pavers.

Wayne Wilmington Ohio roadway Construction Project

Wayne & Wilmington Intersection Improvements

City of Dayton

Value: $2,600,000

Completed in 2011
This project included roadway widening and reconstruction at the Insection of Wayne Ave and Wilmington Ave. in Dayton, OH.

Carver Rd Blue Ash Ohio Roadway Construction Project

Blue Ash - Carver Road Rehab

City of Blue Ash

Value: $1,800,000

Completed in 2014
This project included the replacement of Carver Rd., a sidewalk addition along Reed Hartman Hwy, and the construction & installation of 2 new pedestrian bridges.

Austin Blvd Roadway Construction Project

Austin Blvd. Reconstruction

Montgomery County

Value: $3,450,000

Completed in 2014
This project consisted of widening Austin Blvd. on both sides, the widening of a box beam bridge and installation of a 2×4 box culvert. Other work included: water main lowering and rerouting roadway around the bridge.

MLK High Street Roadway Construction Project

MLK Blvd. & High St. Intersection Improvement

City of Hamilton

Value: $2,550,000

Completed in 2017
This Intersection improvement project included the addition of dual left turn lanes Southbound and a right turn lane Westbound. Project also included the construction of a new Retaining Wall.

Ohio State University (OSU) Roadway Construction Project

OSU Athletics District Road and Storm Water

Ohio State University Columbus, OH

Value: $5,380,000

Completed in 2017
This project included site utilities, storm, water, demolition, abatement, parking lot construction, roadway and box culverts, a wetlands/retention pond along with hardscape and landscaping for OSU Athletics next to Woody Hayes Facility to accommodate new sports complex.

Route 4 Ohio Roadway Construction Project

Route 4 Bypass

City of Fairfield, OH

Value: $9,250,000

Completed in 2013
This project included the widening of SR 4 Bypass from 2 lanes to 4 lanes with additional turn lanes at intersections. The intersection was modified to divert left turn movements via a constructed diversion road. Additional work in the project over CRX Transportation Inc. Railroad crossing included the rehab of the existing bridge structure and the addition of a new bridge adjacent.